The levelized cost of energy (LCOE) is the average cost of producing one unit of electricity over a power plant's entire life, including construction, operation, fuel and financing. It is usually expressed in dollars per megawatt-hour ($/MWh) and is the most common yardstick for comparing the cost of different generation technologies.
The LCOE formula
LCOE = (present value of lifetime costs) ÷ (present value of lifetime electricity generation)
Costs and output are both discounted to today's value, so a megawatt-hour produced in year 20 counts for less than one produced in year 1.
What goes into LCOE
| Input | What it covers |
|---|---|
| Capital cost | Building the plant, often the largest share for solar, wind and nuclear |
| Operation and maintenance | Fixed and variable running costs |
| Fuel | The largest share for gas and coal plants |
| Financing | The discount rate or cost of capital |
| Capacity factor | How much the plant generates relative to its maximum. See capacity factor explained |
| Lifetime | The number of years over which costs are spread |
How to read LCOE comparisons
LCOE answers one question well: what does it cost, on average, to produce a unit of electricity from this asset? Investors and planners also ask when that electricity arrives, how reliable it is and what it is worth to the grid at that moment. Those questions sit outside the LCOE number and call for complementary measures.
The Institute's MERIT™ rating system builds on LCOE to value energy assets by what they deliver to the system as well as what they cost.
Frequently asked questions
What is LCOE?
LCOE, or levelized cost of energy, is the average cost of producing one unit of electricity over a power plant's lifetime, including construction, operation, fuel and financing.
How is LCOE calculated?
Divide the present value of all lifetime costs by the present value of all lifetime electricity output. The result is usually expressed in dollars per megawatt-hour.
What affects LCOE the most?
Upfront capital cost, the cost of financing, fuel prices and the capacity factor, which is how much a plant actually generates compared with its maximum.
What does LCOE leave out?
LCOE measures the cost of energy. The value of that energy depends on when and where it is delivered, which frameworks such as MERIT are designed to capture.
Keep exploring
In the Terawatt Primer: Energy Density and Capacity Factor · GW, MW, kW and kWh Explained · All Primer topics
Go deeper: Beyond LCOE: The MERIT™ Rating System · 3T Index